Have you ever wonder what is the major difference betweent the two type of tasks? Here is a Powerpoint presentation to show the difference.
Here is a quick summary:
Examples of a Fixed Work Task
Based on normal situation, each clerk can prepare 1 document per hour. She can prepare 8 documents per day. If there are 4 persons to work on different documents, there will be a total of 32 documents to be prepared within 1 day. In this case, if our task is to process 32 documents, they can only be completed within 32 man-hours (fixed work effort needed). So, to complete this task, we can assign 4 clerks to prepare 8 documents in one day, or 2 clerks to prepare 16 documents in one day.
Examples of a Fixed Unit Task
If one clerk will only work 8 hours a day (assuming each resource is one unit. Each unit will contribute 8 hours per day), no matter how urgent is the work. If our task is to supply 2 clerks to process the documents for 2 days without considering the urgency of the documents, so for this task, each clerk will work 8 hours in one day and 16 hours in 2 days. Based on our statistics (or estimation), 16 documents should be produced for each clerk. So, we can process 32 documents within 2 days with 2 clerks assigned to the task.
This blog captures some of the thoughts, ideas and things that am learning, researching and exploring on areas such as: Project Management, Software Development, Open Source, etc. Feel free to feedback or comment :)
Subscribe to:
Post Comments (Atom)
Converting a Physical Linux to Virtual
Hmm ... I have done a lot of work on my Linux Lubuntu 15.10 with PHP and PostgreSQL and a few other things ... it is quite time-consuming to...
-
I have got the book: Crucial Confrontation ! It is really a great book. After reading it, I learned a very valuable lesson on how to deal wi...
-
A requirement study stage should not be left "open-ended". There should be key review milestones specified for checking the accura...
-
Here are something to read about PM KPI: KPI explained When we want to create KPIs for PM, we need to use the CSC (Critical Success Criter...
2 comments:
I have been following a site now for almost 2 years and I have found it to be both reliable and profitable. They post daily and their stock trades have been beating
the indexes easily.
Take a look at Wallstreetwinnersonline.com
RickJ
I have been following a site now for almost 2 years and I have found it to be both reliable and profitable. They post daily and their stock trades have been beating
the indexes easily.
Take a look at Wallstreetwinnersonline.com
RickJ
Post a Comment